Slabs-on-Ground
Fiber Reinforcement for Slabs-on-Ground
A project pathway for ground-supported slabs where subgrade, loading, joints, crack-control strategy and construction sequence govern fiber selection.
Design context
Ground support and joints cannot be separated from reinforcement
SubgradeSupport uniformity, modulus and base preparation.
LoadingVehicle, storage, rack and point-load patterns.
GeometrySlab thickness, panels, edges and penetrations.
MovementJoints, dowels, shrinkage and temperature effects.

Construction sequence
Plan batching and finish around the pour
- Ready-mix plant and truck cycle
- Fiber dosing responsibility
- Pumping and discharge method
- Strike-off and finishing equipment
- Saw-cut timing and curing
- Dosage and delivery verification
Prepare a slab-on-ground review
Send slab area and thickness, loads, subgrade, joints, concrete and pour schedule.